June 19, 2012
Plaintiff contracted directly with the owner of a development to deliver trees, and recorded a mechanics lien after not being paid. The court held that plaintiff's mechanics lien was invalid because it failed to provide defendant construction lender with a preliminary 20-day notice under Civil Code Section 3097(b). Section 3097(a), requiring a 20-day notice to the owner, original contractor and construction lender, did not apply because plaintiff was under direct contract with the owner, and the subsection contains an exception for such persons. However, Section 3097(b) requires a 20-day notice to the construction lender by anyone under direct contract with the owner, except "the contractor". The court interpreted that term to refer only to the general contractor, so the exception did not apply to plaintiff.
Cal.App. 5th Dist. (F062924) 5/22/12